Jardine Update

All units are almost complete with final fit out being done including the installation of screens, nurse call buttons, automated locking systems and other technology. 

The ceiling hoists have been installed in unit 1 and 5 and load testing completed.  These are the only 2 units that will have ceiling hoists installed.  The remaining units have the provision in the ceilings to be installed but will be at the participants cost and funded out of their NDIS plan if they require it.

All concrete for paths and driveways have now been poured, including the slab for the BBQ shelter.

Pegging out of the front fence has been completed.

 The hot water cylinders and air conditioning units have been installed.  We have decided to screen the front side of the cylinders for improved aesthetics from the front.

All irrigation piping has been installed for the garden and lawns.

Earthmoving works for the landscaping has commenced as well as some of the pebbles already been put in place. 

All white goods, sleepover beds and linen have been ordered and the kitchen “essentials set up” items purchased. Work has commenced on the staffing roster for Jardine.

The official opening will be on 29 April at 2.30pm.